Vietnam's infrastructure sector: the landscape, opportunities and challenges

Allens Vietnam

The Vietnamese Government has focused on developing infrastructure, but deficiencies in this area are still one of the biggest bottlenecks for investors. In this Report, we look at the current status of the infrastructure market, and examine key regulatory and structuring issues affecting project developers and financiers.

What you need to know about Vietnam's infrastructure market

In this context, it’s no surprise that Vietnam's Government has focused on developing infrastructure to underpin socio-economic development strategies. Despite this, and significant progress over the past two decades, infrastructure deficiencies are one of the biggest bottlenecks for investors in Vietnam.

Against this backdrop, and as Vietnam has developed and moved out of low-income country status, the means of financing infrastructure has shifted away from official development assistance and soft loans towards a heavy emphasis on private financing. Over time, this has been illustrated by the development of Vietnam's infrastructure-related regulations.

In this Report, we look at the current status of the infrastructure market, with a focus on particular sectors. We also examine key regulatory and structuring issues affecting project developers and financiers.

Key themes

Growing opportunities

With its economy growing strongly, Vietnam's need for infrastructure is increasing across a wide range of sectors, opening up numerous opportunities for infrastructure developers, investors, lenders and service providers.

A complex legal environment to consider

While the need for high-quality modern infrastructure in Vietnam continues to grow, the legal environment underpinning projects is becoming increasingly complex and nuanced – presenting a number of changes and challenges to consider.

Balancing private and public interest

In 1993, Vietnam first issued regulations regarding investment through build-operate-transfer (BOT) projects (applicable to foreign investors). Since then, there have been numerous iterations of the regulations – each striving to find a balance between private and public interests, with varying degrees of success.

In general

As of January 2019, 336 PPP projects were implemented in Vietnam, with total investment capital of more than VND1,600 trillion (c. USD 69 billion)1. Most of these projects were carried out using either the BOT form (42%) or build transfer (BT) form (56%). A considerable majority (220 projects; approximately 65% of the total number) were in the transport sector – primarily roads. The next most common sector was power, with 19 projects.

Below, we provide a snapshot of the current status of the following key infrastructure sectors: power, gas, roads, ports, airports and petrochemicals.

Power

In Vietnam’s power sector, private sector investment has been carried out in either the PPP form (primarily using BOT structures) or as independent power projects (IPPs) outside of the PPP regulations. In recent years, there has been significant foreign investment in renewable energy, either through direct IPP investment or from the acquisition of existing assets from local developers.

An energy project can only be developed if it has been included in a 'power development master plan'. In line with the Law on Planning, there is a national power development master plan. Each province also has a provincial master plan, with a section on power complementing the national plan. While both plans need to be approved by Vietnam's PM, the national power development master plan is developed by the Ministry of Industry and Trade (the MOIT). Provincial master plans are developed by each province and appraised by the Ministry of Planning and Investment (the MPI).

The current approved national power development master plan is the PDP7 (revised), which covers the period from 2011 to 2020 with a vision to 2030. The next national power development master plan (the PDP8) is currently being drafted. The PDP8 will establish the direction of power development from 2030 up to a vision of 2045. Following Vietnam's announcement at COP26 of a 2050 net-zero emissions target, the Government has requested the MOIT to collect more opinions from experts, scientists and localities to make PDP8 fit for purpose. While the issuance date is unknown, it is expected in Q1 of 2022.   

According to the most recent draft of the PDP8 (November 2021), the total installed capacity must be capable of meeting the maximum power demand of Vietnam as a whole. However, the currently planned development pipeline is not compatible with the consumption and supply growth within each of the Northern, Central and Southern regions.

The growth in demand in the north is the highest (around 9.3% per year for the 2016-20 period) while supply-side growth is the lowest among the regions at 4.7% per year.2 The demand and supply-side growth for the same period in the centre is 5.3% and 16% per year, and in the south,  6.8% and 21% respectively.3 This incompatibility between demand and supply is driving specific policies for the development of particular power sources and the approach to transmission in each of the regions. In line with the November 2021 draft of the PDP8, the national total installed capacity is expected to reach around 155,722 MW by 2030 and 333,587 MW by 2045.

We have set out the allocation of power sources in the chart below.

 

 

  • PPP power plants
  • IPP power projects
  • Renewable energy projects
  • LNG-to-power

Currently, only two BOT gas-fired power plants (Phu My 2.2 (715MW), Phu My 3 (720MW)) and four BOT coal-fired power projects (Mong Duong 2 (1,240MW), Vinh Tan 1 (1,240MW), Hai Duong (1,200MW) and Duyen Hai 2 (1,320MW)) are in operation. Nghi Son 2 (1,200MW), Van Phong 1 (1,200MW) and Vung Ang 2 (1,200MW) coal-fired power projects have achieved financial close and are currently under construction.4

Despite the instruction from the Politburo in Resolution 55, and Vietnam's net-zero announcement, the planned installed capacity for coal-fired power plants in the November 2021 draft of the PDP8 remains high – 39,699 MW by 2030 and 43,149 MW by 2045 for the high-load case, which accounts for 25.49% and 12.9% of the total national installed capacity respectively.5 However, these figures have been reduced from 40,899 MW by 2030 and 50,949 MW by 2045, which accounts for 28.43% and 15.5% respectively, as set out in the draft PDP8 released in October.6 It remains to be seen how much new coal-fired power capacity will ultimately be able to be financed and constructed.

Roads, ports, airports and rails

As noted above, transportation projects account for a significant majority (65%) of the total number of PPP projects implemented, or set to be implemented, in Vietnam to date. Of the 220 transport sector PPP projects, 132 (60%) are already in operation, with the rest at various stages of development.10

These projects have been mainly carried out in BOT and BT forms, the vast majority (96%) being road projects.

  • Roads
  • Seaports
  • Airports
  • Railways

The Vietnam Government is keen to accelerate the development of expressways. For the period 2021 to 2030 with a vision to 2050, it aims to have 41 expressways with a total length of 9,014 kilometres across Vietnam.11

To date, despite substantial interest, there has been limited involvement of foreign investors in road projects (no road projects are wholly-owned and/or operated by foreign investors, and only one has any substantial foreign investment). Foreign involvement is typically limited to providing services and financing.

Refinery/Petrochemicals

Vietnam currently has two large operational refineries:

  1. The Dung Quat Oil Refinery in Dung Quat Economic Zone, Quang Ngai. It was developed by PetroVietnam with total investment capital of about USD 3 billion, and a capacity of 8.5 million tons per year.
  2. The Nghi Son Refinery in Nghi Son Economic Zone, Thanh Hoa. It was developed by four sponsors (PetroVietnam, Idemitsu Kosan Co. Ltd., Mitsui Chemicals Inc. and Kuwait Petroleum Europe B.V.) with total investment capital of more than USD 9 billion and a capacity of 10 million tons per year.

In addition, the Long Son petrochemical complex is under construction in Ba Ria – Vung Tau province. This project has total investment capital of around USD 5.4 billion, with the sole investor being the SCG group from Thailand.

The Vietnamese Government has indicated it aims to attract more investment in the refinery and petrochemical sectors to increase its value-add processing activities, and improve the quality of petroleum products. In all, Vietnam intends domestic refineries to meet at least 70% of total national demand.19

Considering your investment form options

It is not mandatory for infrastructure projects to be carried out in the PPP form. While there are advantages and disadvantages to consider, the major benefit of investing under the PPP regime is it provides a specific regulatory pathway to seek government guarantees and support (though now on a limited basis) that will enhance project viability, mitigate risk and support financing.

While it is theoretically possible for the Government to offer such support to infrastructure projects done outside the PPP regime, there are limited precedents for this. Plus, investors face the uncertainty of direct negotiation. So far, we are aware of only two cases where the Government has provided government guarantees and undertakings (GGU) for megaprojects not carried out in PPP form. In another IPP, the Government issued a guarantee for the loan obtained by the project company (for repayment obligations only).

PPP or non-PPP?

From a bankability perspective, some of the regulations provide more favourable treatment for investment in the PPP form than the non-PPP form. Here's why:

  • The PPP Law provides that the Government can decide on issuing guarantees on foreign currency for key PPP projects, with the investment policy decided by the National Assembly or the PM subject to (i) foreign currency policy and the capability of the state to manage foreign currency reserves, and (ii) the 30% threshold for foreign currency support for VND project revenue (to be converted into USD) after deducting local expenses;
  • In addition to foreign currency availability and conversion, the PPP scheme expressly provides for more guarantees and support from the Government, including priority access to public facilities and services, a mechanism for sharing revenue increases and shortfalls, and lenders' step-in rights;
  • There is more room for the investor to negotiate bankable contracts in the PPP scheme. Specifically, the PPA for power projects does not have to follow a particular statutory form. Although the PPP contract has to follow a model form (which so far has only been issued in the form of guidance), a PPP contract by its nature allows the investor to shift certain risks to the Government side; and
  • In practice, there is ample precedent of international financing on a non-recourse basis of power projects in the PPP form. Many international lenders are familiar with the project documents and the key risks (although it remains to be seen whether financiers will be as ready to finance projects under the requirements of the new PPP Law).

There are other considerations when comparing PPP and non-PPP regimes in the current environment:

  • For non-PPP projects, it is less clear if a GGU will be on offer. Decree 311 states that subject to the socio-economic development conditions and the need to attract investment for each period, and the scale and nature of each project, the PM may decide the format and contents of a guarantee to be issued for (i) projects where the investment policy is decided by the National Assembly or the PM, or (ii) other important infrastructure projects. Decree 31 provides that such a guarantee can be in the form of (a) foreign currency support, or (b) other state guarantees as decided by the PM.
  • Although Resolution 55 stated that energy investment projects are encouraged to be implemented in the PPP form, it appears that the PPP form is not preferable as a matter of practice in certain sectors. For example, of the various LNG-to-power projects recently proposed to be carried out, we are aware of only two projects proposed to be in the PPP form, and the Government appears to prefer that LNG-to-power projects are carried out as IPPs;
  • History shows that negotiation of project documents in the PPP context can be very long and drawn out;
  • The PPP Law sets out a brand-new regime that has not been tested in practice, so the investor should expect currently unknown hurdles and delays along the way;
  • The non-PPP scheme offers some advantages that may be more attractive to the investor than those under the PPP scheme. For example, the law clearly provides that in certain cases, the selection of an investor through bidding is not needed; and
  • Other advantages of the non-PPP scheme include longer project life, no requirement to later hand over the project to the Government, no statutory time limit for securing finance, less stringent transfer conditions, and the possibility of some key contracts being governed by foreign law.

Investment cycle

Below are outlined the phases for investment under the PPP regime and the general investment law regime.

A PPP project must be included in the relevant master plans before the pre-FS can be formulated. Under investment law, a non-PPP project does not have to be included in a master plan,2 except for power (including LNG-to-power) and gas projects which must first be included in a power master plan (as has been the law and practice so far). Subject to this exception, an investment policy approval for a non-PPP project can be issued if the project complies with relevant master plans.

PPP project cycle

A PPP project cycle consists of the following phases:

PHASE 1: PRE-FS REPORT, INVESTMENT POLICY APPROVAL (IPA), PROJECT ANNOUNCEMENT
  • Pre-FS report to be formulated by:
    • the body authorised by the authorised agency, or
    • the investor (in case the project is proposed by the investor);
  • Pre-FS report to be evaluated by the PPP Evaluation Council;
  • IPA to be issued by:
    • the National Assembly,
    • the PM, or
    • the Ministers of ministries or the provincial PC;
  • Project announcement.
PHASE 2: FEASIBILITY STUDY (FS) REPORT AND PROJECT APPROVAL
  • FS report to be formulated by:
    • the body authorised by the authorised agency, or
    • the investor (in case the project is proposed by the investor);
  • FS report to be evaluated by the same PPP Evaluation Council as mentioned in Phase 1.
PHASE 3: SELECTION OF INVESTOR
  • The selection of investor can be via:
    • public tender;
    • competitive negotiation;
    • direct appointment of investor; or
    • other methods in special cases.
  • Generally, public tender shall apply. The investor shall enjoy preferential treatment in the tender if it:
    • proposes the project;
    • undertakes to use domestic contractors for work accounting for at least 25% of the total investment capital of the project; and/or
    • undertakes to use domestic equipment and materials with a value accounting for at least 25% of the total investment capital of the project.
  • Competitive negotiation only applies in the case:
    1. there are no more than three investors satisfying the requirements for project implementation;
    2. the project is a hi-tech application project given priority for development; or
    3. the project applies new technology in accordance with the laws on technology transfer.
  • Direct appointment of investor only applies in the case:
    1. the requirement for national defence and security or state secret needs to be ensured, or
    2. replacement of an investor.
PHASE 4: PROJECT COMPANY ESTABLISHMENT AND SIGNING OF PROJECT CONTRACT
  • Establishment of the project company shall comply with the Law on Enterprises;
  • The PPP project contract is entered into between the project company, the investors and the contract signing agency;
  • Payment of performance security deposit;
  • Equity of the investors must be contributed in accordance with the schedule as agreed in the PPP project contract.
PHASE 5: PROJECT IMPLEMENTATION, ACCOUNTING FINALISATION, TRANSFER OF FACILITY AND LIQUIDATION OF PROJECT CONTRACT 
  • The project company shall formulate and promulgate rules to select contractors for the implementation of the project.
  • The project company shall be responsible for construction quality management and supervision, under the supervision of the authorised state body
  • The accounting finalisation shall be carried out after completion of construction.
  • The handover of the project facility shall comply with the agreed conditions and procedures set out in the project contract.

Investment project cycle under general Investment Law regime (Non-PPP project cycle)

An investment project cycle under the general Investment Law regime consists of the following phases:

PHASE 1: FORMULATION OF INVESTMENT PROJECT PROPOSAL

Formulation of the investment project proposal (where construction laws require the pre-FS to be formulated, the pre-FS could be used in place of the investment project proposal).

PHASE 2: INVESTMENT POLICY APPROVAL (IPA)
  • IPA to be issued by:
    • the National Assembly;
    • the PM; or
    • the provincial PC.
PHASE 3: SELECTION OF INVESTOR
  • The selection of investor can be via:
    1. auction of the land use right (LUR) in accordance with regulations on land;
    2. tendering in accordance with regulations on tendering; or
    3. approval of investor.
  • Generally, auction of LUR applies in the following cases:
    • land lease or land allocation to implement the project is subject to auction of LUR under law on land; and
    • the proposed area of land for project implementation has already been cleared.
  • Tendering applies in the following cases:
    • the project does not satisfy the conditions for auction of LUR as stated in the preceding bullet point; and
    • the project is subject to tendering for selection of investor under the law on tendering, the law on socialisation or specialised laws.
  • Approval of investor applies in the following cases:
    • the LUR auction has been conducted but only one investor registered for participation;
    • the LUR auction in accordance with land regulations fails twice;
    • tendering is conducted to select investors, but only one investor registers for participation in the tendering and satisfies preliminary requirements for capability and experience. Or, various investors register but only one satisfies preliminary requirements for capability and experience;
    • the investor has LUR, except for the case where the state expropriates land for national defence and security purposes, or for socio-economic development in the national or public interest in accordance with regulations on land;
    • the investor has LUR via LUR transfer, capital contribution, lease of agricultural land for implementation of non-agricultural investment project for production or business that is not subject to land expropriation by the state in accordance with regulations on land;
    • the investor implements the investment project in an industrial park or hi-tech zone; or
    • other cases not subject to an auction or tendering in accordance with law.
PHASE 4: INVESTMENT REGISTRATION CERTIFICATE (IRC), ENTERPRISE REGISTRATION CERTIFICATE (ERC)
  • IRC shall be issued after issuance of IPA, except for projects that do not require an IPA.
  • Establishment of the project company shall comply with the Law on Enterprises.
PHASE 5: PROJECT IMPLEMENTATION
  • The investor shall pay a security deposit for project implementation of 1-3% of the investment capital of the project.
  • The project term shall be no more than 50-70 years, depending on the location of the project. Upon expiry of such term, the investor may apply for extension of the term.

Project structure

While no two projects are the same, and each requires careful consideration in terms of structuring, the below diagram illustrates a typical contractual structure for a PPP project implemented using project finance. In Vietnam, a number of BOT/PPP power projects have been successfully financed by international lenders using this structure, though not under the current PPP Law.

In a non-PPP project, to obtain international financing a similar contractual structure is expected, except that there may be no project contract1 and GGU.

19325D graphs_2-contractual-structure_D.jpg

Financing structures

Project finance

Project financing is the provision of funding for a discrete single-purpose investment on a non or limited-recourse basis, with repayments principally being made from the income streams generated by such investment. So far, large-scale infrastructure projects in Vietnam have typically been financed on a non or limited-recourse project finance basis.

Typical sources of funding for large infrastructure projects have come from commercial banks (including international and local banks), development finance institutions, export credit agencies, bonds, equity, packaged up with additional credit support such as completion guarantees, performance bonds, deferred payments, and insurance.

Bankability issues

Key bankability issues

Infrastructure projects commonly face issues and risks that can't be effectively mitigated or addressed without involvement from third parties – notably, the state. While many investors have sought GGUs to backstop certain risks (eg state-owned entity obligations, currency availability and convertibility), the Government has only agreed to them in a limited number of cases for projects considered to be nationally significant (around 10 so far). In recent years, the scope of GGUs has become more limited as the Government seeks to reduce its exposure to privately-funded projects, claiming that improvements in the country's legal system and general market conditions don't justify the previous levels of support.

Below, we identify the top 10 issues we see affecting the bankability of infrastructure projects in Vietnam, and comment on how they might be addressed in a GGU – via PPP project contracts or otherwise.

Vietnam-infra-banking_1-nationalisation.png

Nationalisation and compensation

Though rare, nationalisation is a major government risk for foreign investors. While protection against nationalisation is provided in domestic law and international investment treaties, this protection is often not adequate for specific projects, and needs to be further addressed in project agreements.

Notably, in recent draft GGUs, a guarantee against nationalisation has been absent. In PPP project contracts, nationalisation would usually be treated as a Government event for which full compensation is payable.

Political risk insurance, from private and/or multi-lateral sources such as MIGA, might also be a tool to manage nationalisation risk.

Vietnam-infra-banking_2-documents.png

Legality of project documents

The risk of project contracts not being valid or permits being challenged is best mitigated by a specific Government commitment that the documents, as well as rights and assets created under them, are valid and lawful under Vietnamese law. This might take the form of a legal opinion provided by the Ministry of Justice, relied on by investors and lenders. If a key document is found to be invalid, unenforceable or terminated, it would then become a Government event for which compensation is payable.

Vietnam-infra-banking_3-changes.png

Changes in law or policy

In recent years, protection against changes in law for BOT power projects has been included in BOT contracts. This regime provides contractual protection to investors from unfavourable changes in law. Investors may also be asked to share with the state the benefits that arise from a favourable change in law.

The guidance for formulating model contracts in Decree 35 states that the model contract will provide for contract amendments in the case of change in law or policies. It also states that the model contract will regulate, amongst other matters, changes in law or policies that affect the implementation of the project contract and the revenue loss sharing.

Protection of this nature for non-PPP projects is limited to the protections set out in the Law on Investment. There is no clear precedent to date as to how willing the authorities will be in negotiating a change in law clause in a project contract (if any) if a project is implemented on a non-PPP basis.

Vietnam-infra-banking_4-approvals.png

Approvals and permits

There is currently no protection available under domestic law or investment treaties for difficulties or delays obtaining relevant approvals and permits for a project. PPP project contracts and/or the GGU may provide Government commitments to assist investors with procedures. Again, this support is limited in practice and is unlikely to be expressly forthcoming for non-PPP projects.

Vietnam-infra-banking_5-foreign-currency.png

Foreign currency conversion

At the start of Vietnam's PPP regime, the Government was expected to provide foreign currency availability and conversion guarantees for 100% of the project's foreign currency needs. More recently, such guarantees have been limited to 30% of Vietnamese Dong revenue after deducting local expenses. This 30% limit has now been enshrined in the new PPP Law.

Foreign currency guarantees can also be given under the general investment law regime if there is appetite from the Government to give support. It is expected that the 30% threshold will still apply in such cases, although the law does not limit it expressly.

Private currency hedge products may be available to mitigate this risk, but obviously come at a cost that can adversely affect project economics.

Vietnam-infra-banking_6-guarantee.png

Guarantee of performance by state entities

Many projects rely partially or wholly on revenue streams from state-owned offtakers. If they default on their obligations, payment or otherwise, projects can quickly grind to a halt. Previously, the Government was willing to provide full guarantees of state-owned counterparty obligations to give comfort to investors and lenders. However, in keeping with contemporary policy, the Government now seeks to  significantly limit the scope of such guarantees, arguing that the market should make its own risk assessment based on past performance and credit ratings of state entities such as EVN.

In practice, the Government may negotiate limited guarantees of financial obligations of key state entities for some major projects. But, again, it is difficult to see such guarantees being offered outside of the PPP regime, and even then, it would be in only highly nationally significant projects.

Vietnam-infra-banking_7-foreign-law.png

Governing law: Vietnamese law vs. foreign law

Foreign investors and lenders have indicated a strong preference for a well-developed foreign law, such as English or Singaporean law, to govern key project contracts, in order to provide maximum certainty. Vietnamese counterparties typically advocate strongly for Vietnamese governing law, arguing that they are more familiar with it, that the projects take place in Vietnam and that the law itself is sufficiently developed.

The practice to date has been for PPP project contracts to be governed by foreign law. However, the new PPP Law provides that Vietnamese governing law will be mandatory for the PPP project contract and any contract entered into between a Vietnam state body and investors or the project company. This means that under the PPP regime, foreign law can no longer be the governing law for the GGU and project contract.

Vietnam-infra-banking_8-dispute-resolution.png

International dispute resolution and enforcement of arbitral awards

As Vietnam is a party to the New York Convention on Recognition and Enforcement of Foreign Arbitral Awards, it has agreed to allow enforcement of arbitral awards made in, or by, an arbitral tribunal of a country that is also a party to the Convention. However, the process requires recognition and enforcement by the courts of Vietnam (which have been known to refuse awards on the grounds that the process or award fails to comply with 'fundamental principles of Vietnamese law'). Since such principles are not clearly defined, Vietnamese courts have significant discretion in practice when it comes to enforcing a foreign arbitral award.

Vietnam-infra-banking_9-early-termination.png

Early termination payments

Under the PPP Law, early termination payments are allowed only in very limited circumstances – specifically, when a PPP project contract is terminated due to national interest requirements, national defence and security and protection of state secrets, or when the contract signing agency is materially in breach of the contract. However, there is no formula for calculating the termination payments in these cases, so they would need to be negotiated on a bilateral basis.

The PPP Law appears to provide for only two scenarios where termination payments can be made – for national interest, to ensure national defence and security or to protect state secrets; and in case of breach by the contract signing agency. Decree 35 seems to allow the project contract to provide for termination payments in all cases. However, Decree 35 cannot go outside the ambit of the PPP Law, so there may not be much room for investors to negotiate this issue on the basis of Decree 35's apparent broader ambit.

It is critical that project sponsors negotiate clear and detailed agreements on termination payments in project documents. Essentially, a termination following a breach by Government parties should entitle the sponsor to a payment that sufficiently covers all equity and finance costs, plus an agreed return on equity. While termination payments by the sponsor or project company are more vexed, ideally the sponsor should be seeking to cover at least its financing costs. Termination following force majeure will usually have a separate regime, depending on which party is affected by it.

Vietnam-infra-banking_10-restricitions.png

Security gaps

In terms of project financing, lenders may be limited by certain restrictions on the security package they are able to take under Vietnamese law. This impacts the feasibility and/or cost of non-recourse financing. These restrictions include:

  1. Restriction on mortgage over land: Land users paying rent annually or entitled to a waiver of land rent (either partially or wholly), as opposed to full payment of the land rent upfront for the whole term, may not mortgage or contribute their land use rights as capital in the project company (but may mortgage or contribute assets attached to the land).
  2. Restriction on mortgage over land and assets attached to land with foreign lenders: Foreign lenders are not permitted to take security over land and assets attached to land in Vietnam. Only Vietnamese licensed credit institutions (which include Vietnamese branches of foreign banks) are permitted to take mortgages over land and assets attached to land in Vietnam (in respect of their own loans and not on behalf of a foreign lender or in respect of a foreign loan). While various creative structures are often considered to navigate this restriction in practice, none have been properly tested in practice.

Other key Vietnamese law issues related to financing

number_teal-80x80px-1.png Borrowing limits – Under Vietnamese law, a borrower issued with an 'investment policy approval' and/or an 'investment registration certificate' approving its investment project may only borrow long-term funds (ie borrowing with repayment terms of a year or more) to implement that project – up to the limit of the difference between the borrower's equity and the total amount of registered investment capital specified in its investment registration certificate.
number_teal-80x80px-2.png Overall national borrowing limit – There is an overall limit on the total amount of foreign loans for the whole country approved by the PM for each year. Technically, if the national loan limit for the year (which we understand is around USD5.5 billion/year) is exceeded, registration of the loan, a prerequisite to disbursement of long-term loans, may be refused by the State Bank of Vietnam.
number_teal-80x80px-3.png Thin capitalisation – In line with the PPP Law, an investor's equity ratio must be no less than 15% of the total investment capital of the project.

There is also a thin capitalisation requirement for non-PPP project companies using land leased from the state, being 20% for projects using a land area of less than 20 hectares and 15% for projects using 20 hectares or more.

There may also be further thin capitalisation requirements in line with regulations governing specific sectors. Project lenders will also impose their own equity controls as a condition of finance.

Final words

Although the need for high-quality modern infrastructure in Vietnam continues to grow steadily, the legal environment underpinning projects is becoming increasingly complex and nuanced. In particular, the PPP Law has introduced a number of changes that will have a material impact on projects. This includes those that were already in advanced development stages before its effectiveness. The changes have not yet been tested, and it will take time to see how these play out in practice.

The policy position enshrined in the PPP Law is that private investors and lenders ought to share more risk with the state. Put another way, the Government's position is that, as Vietnam and its legal system and markets mature, the Government should have less responsibility to backstop project feasibility. While this is a reasonable position, it remains an open question whether the market will accept it; and, just as importantly, how positions will develop between lenders seeking certainty and sponsors seeking to develop and operate projects that stand or fall on their own merits, without recourse to parent company balance sheets.

FOOTNOTES

  1. Report 25/BC-CP of the Government dated 30 January 2019 on status of implementation of investment projects in the form of public-private partnership (Report 25). To our knowledge no further updated report has been prepared.

  2. Reference materials in the MOIT workshop to collect opinions to complete the draft PDP8, November 2021, page 4.

  3. Reference materials in the MOIT workshop to collect opinions to complete the draft PDP8, November 2021, page 5.

  4. Report 32/BC-BCT, page 9

  5. Reference materials in the MOIT workshop to collect opinions to complete the draft PDP8, November 2021, pages 22 and 24.

  6. Reference materials in the MOIT workshop to collect opinions to complete the draft PDP8, November 2021, pages 18 and 20

  7. Article 1.3(a) of the revised PDP7.

  8. Reference materials in the MOIT workshop to collect opinions to complete the draft PDP8, November 2021, page 22.

  9. Reference materials in the MOIT workshop to collect opinions to complete the draft PDP8, November 2021, page 22.

  10. Report 25.

  11. Decision 1454/QD-TTg of the PM dated 1 September 2021 on approval of the master plan for the road network for the period up of 2021 to 2030 with a vision to 2050.

  12. Decision 1579/QD-TTg of the Prime Minister dated 22 December 2021 approving the master plan for development of Vietnam's seaport system for the period of 2021 to 2030 with a vision to 2050.

  13. https://www.vietnam-briefing.com/news/port-infrastructure-vietnam-3-hubs-for-importers-exporters.html/

  14. Transport Ministry proposes allowing private firms to invest in airport projects (vietnamnet.vn)

  15. Resolution 556/NDQ-UBTVQH14 dated 31 July 2018 of the Standing Committee of the National Assembly, available here

  16. http://baochinhphu.vn/Kinh-te/Ha-tang-duong-sat-gia-nua-Giai-phap-nao-de-thu-hut-von/376009.vgp

  17. Nghiên cứu thêm phương án đường sắt cao tốc Bắc - Nam tốc độ 200 km/giờ | Tài chính - Kinh doanh | Thanh Niên (thanhnien.vn)

  18. Decision 1259/QD-TTg of the PM dated 26 July 2011 issuing master plan for construction of Hanoi capital up to 2030 with the view to 2050 and Decision 568/QD-TTg of the PM dated 8 April 2013 on approval of adjustments to the master plan for transportation development of HCMC up to 2020 with the view to after 2020.

  19. Section II.2(b) of Resolution 55- NQ/TW of the Politburo of Vietnam dated 11 February 2020 on the orientation of the National Energy Development Strategy of Vietnam to 2030, with a vision to 2045 (Resolution 55).

 

Please Login or Register for Free now to view all updates and articles

In addition to free-to-view updates and articles, you can also subscribe to the full Legal Centrix Vietnam Service including access to:

  • Overview notes on the law
  • Thousands of high quality translations of legislation covering all key business areas
  • Legal and tax updates
  • Articles on important legal and tax issues
  • Weekly email alerts
  • Sophisticated web platform and search

Legal Centrix is trusted by top law and accounting firms.

Allens Vietnam

Allens is a leading international law firm in Vietnam. Our office was one of the first foreign law firms to be licensed after Vietnam opened up to the world in 1993. Since then, we have acted on some of Vietnam's most important large-scale projects and commercial transactions.

Our services span the full suite of legal practice areas, including:

  • Mergers and aquisitions 
  • Energy, resources and infrastructure
  • Banking and finance
  • Capital markets transactions
  • Anti-trust and merger filing
  • Construction and EPC
  • Corporate and licensing

Your trusted advisers in Vietnam

We practice both local and international law in Vietnam. Our team of international and Vietnamese lawyers is geared towards sound, efficient and timely advice. The depth of our experience in Vietnam means we can identify issues and find practical solutions, all while taking local sensitivities into account.

Our global reach and Asian network

Allens' international alliance with Linklaters ensures we can serve our clients throughout Asia and globally, wherever their business takes them, through a global network of 40 offices across 28 countries.

Click here to view the author's profile

Author

Related Content

Tags

  • Vietnam
  • Lending
  • Energy, Electricity, Oil & Gas
  • Project Finance
  • Vietnam Laws & Regs
  • Shipping & Transport

Recent updates

Cookies On
Our Website
We use cookies on our website. To learn more about cookies, how we use them on our site and how to change your cookie settings please click here to view our cookie policy. By continuing to use this site without changing your settings you consent to our use of cookies in accordance with our cookie policy.